To show that all or part of the work on a task is complete:
-- part contents for background part 6
----- text -----
Place the pointer at the left border of the task’s actual bar.
When the pointer is positioned properly, it changes to an outlined crossbar.
If the bar is already partially black, place the pointer at the right edge of the black area.
-- part contents for background part 27
----- text -----
1.
-- part contents for background part 7
----- text -----
Drag to the point that represents the proportion of work completed (all the way to the right if the task is
completed).
The completed portion of the bar turns black. While you are dragging, a number appears at the lower-left corner of the bar indicating the percentage completed.